Preface
In September 2024 NHR@ZIB will replace the global file systems HOME and WORK in all systems of Lise in Berlin. This affects all login nodes and all Compute partitions. Please be aware of the following activities.
For September we plan a maintenance to replace the file systems HOME and WORK.
Each user has the opportunity to migrate data from the old to the new WORK file system.
All data in the HOME file system will be copied by NHR@ZIB. The user does not have to do anything on the HOME file system.
Time schedule, last update July 15th
date | subject |
---|---|
Aug 26th | email update for migration plan |
Sept | 3 day maintenance for replacement of HOME and WORK |
Sept/Oct | 3 week migration phase to copy data from old to new WORK |
Data migration for WORK
Data migration for the WORK file system follows the following steps.
Migration phase
This is a 3 week period in September.
You have access to two different WORK file systems, the old and the new one.
The new WORK file system is empty and you are invited to copy data to the new WORK file system.
NHR@ZIB staff will not copy any data to the new WORK file system.
After the end of the migration phase
the new WORK file system is available for each user.
the old WORK file system is switched off and all data will be removed.
Remarks
PERM file system is not affected by this maintenance. During all times of operation of system Lise, PERM will be available all each user.