One-week downtime for maintenance, preparation steps, and for preliminary transfer of HOME data. NHR@ZIB staff copies all data from the old to the new HOME storage. No user action is required.
One-day maintenance of the entire system for a final synchronization step between old and new HOME. Old HOME goes offline, new HOME goes online. No user action is required.
Two-month Migration phase for WORK migration phase for data in WORK. During this period, both the old and new WORK file systems are available. Users transfer their data from the old to the new WORK storage.
...